
Permits in hand, we were ready to begin work. We got our culvert and temporary access (i.e., our driveway) installed, then had the surveyors place pins for excavation, and sought official quotes for excavation. This was the source of our first major snafu.
We were expecting that excavation would be no sweat, our land was relatively flat after all and we didn’t need to dig a basement. However, while chatting with the person installing the temporary access, he mentioned that from our grading plan, it looked like we were importing an awful lot of fill. This was an understatement. When the quotes came back, it was about $100,000 worth of fill, not to mention the labour to install it and the gas to ship it. We were floored. This could be a knockout blow before we even started. It also wasn’t what we wanted, our house would have towered over the landscape, perched on a hill we built.
Thinking it over, a few things brought us to this point:
- We decided to build a raft slab foundation. Our project manager had recommended it to save cost and our architect agreed. This is a foundation that essentially floats on the ground. You insulate on all sides of the slab, obviating the need for footings below the frost line. It isn’t the norm for this area but is becoming more common. And it seemed to make sense for our house and our land, where there’s bedrock close to the surface. It would save us having to blast.
- Because it’s an unusual construction type, the foundation seemed to stump a few people, including our grading designers, who designed the grading similar to how it would typically be done (like in a house with a basement). We would have appreciated a discussion of the different options and implications.
- Our lack of experience and construction knowledge meant that we didn’t glean any of this from the grading plan – and it wasn’t obvious to anyone else involved (or wasn’t flagged if it was).
- Because the subtrades weren’t willing to provide quotes ahead of time, our project manager’s estimate was based on previous jobs rather than our specific circumstances and ended up missing the mark.

We had to get the septic and grading plan amended and resubmit for approval. The whole process set us back over a month. Our excavation cost was, in the end still higher than originally estimated, but we hope to make it up in other ways along the way. We’re just happy we didn’t have to build our own mountain.
Finally, in August 2022, we had our pad and were ready to start the structure!
We did hit another hit another minor snaggle with excavation when the surveyors came in to pin the foundation. They thought the excavator put the pad in the wrong place. We checked and it was exactly where we wanted it, so if that was a mistake, it was a happy one for us, though it did lead to a little finger point between the subtrades. You win some, you lose some.

